PROJECTS

Water Main Installation
End of horizontal directional drill

Water Main Installation
Trenching during installation

Water Main Installation
Deflection to avoid utility conflict
Because HCPUD sought to keep its water customers uppermost in all elements of the project, the project approach included a strong community focus and high sensitivity in minimizing impacts to the community. At the onset of the project a detailed Community Outreach Plan was prepared. The project is currently under construction, and progressing smoothly. HCPUD has requested that the design-build team handle the design and construction of all plumbing connections to each individual water user. The design build team is working with each individual property owner to appropriately place the new water service line from the back side of the meter to the house. The team is also coordinating with the County Building Department for permit approvals and inspections. The cost of the project was $8.84 million dollars.

32nd Avenue
Installation of a 16-inch water
main

El Centro Street
Installation of stormwater
structures

Gulf Boulevard
Force main tie-in
MWI provided a full-time senior inspector to observe construction activities, prepare daily reports, monitor contractor schedule, witness testing, maintain a log of materials, record meeting minutes, review and track pay requests, and report any deficiencies or work requiring correction. MWI also had the responsibility of working with the business owners and residents to ensure access was maintained.
The construction cost of the project was $11.0 million dollars.

51st Avenue East
Grading and forming for 6-foot sidewalk

28th Street West
Installation of a 6-inch storm
water underdrain

54th Avenue West
Grading preparations for
installation of asphalt base
MWI provided a Senior Level Inspector for a period of 548 days to observe the Contractors work on-site, manage materials testing, and to fulfill other construction management duties including administration, measurement and payment, and project close-out. The MWI Senior Inspector was responsible for recording daily field observations, including field tests and measured quantities of pay items in accordance with the approved schedule of values; reviewing contractors monthly pay requests; obtaining and monitoring contractor schedules; taking photographs of on-going construction activities; reviewing and checking construction in progress, constructed work, and materials and equipment; conducting and observing testing, and attending and participating in regular construction progress meetings.
The construction cost of the project was $4.7 million dollars.

Lithia Facility
Side Stream Pump Station

Lithia Facility
Ozone Dissipation Chambers

Lithia Facility
Ozone Generator Building
MWI participated in preparation of a project plan and permitting strategy including attendance at kick off meetings and workshops; and prepared the civil site components for the preliminary design package including site lay-out, drawings, specifications, typical details, cost estimates and construction schedule input. MWI also prepared a permitting matrix and submittal schedule and conducted a preliminary wetlands determination and survey. MWI supported property acquisition for the site and numerous easements by preparing sketches and legal descriptions. Following selection of the EPCM contractor MWI reviewed civil components of the design, and monitored and supported permitting efforts. During the construction phase MWI provided a full time resident project representative to monitor all construction activities.
The cost of the project was $28.2 million dollars.

Belcher Road
Installation of cast in place pipe
liner

Woodland Boulevard North
Stormwater structure repair

South Cross
Cast in place liner by hot water method
MWI provided a full-time Senior Inspector to observe the construction contractors’ work on-site and to fulfill other construction management duties including meeting administration, schedule administration, measurement and payment administration, and project close-out. The Senior Inspector was responsible for recording daily field observations, including field tests and measured quantities of pay items in accordance with the approved schedule of values; reviewing contractors monthly pay requests; obtaining and monitoring contractor schedules; taking photographs of on-going construction activities; reviewing and checking construction in progress, constructed work , and materials and equipment; conducting and observing testing, and attending and participating in regular construction progress meetings.

US 41 Force Main
Trenching in right of way for
utility installation

Typical Trench
Work performed in dry trench

Plug Valve Installation
Force main with new plug valve
The complete project included 6,110 LF of 8-inch fusible PVC force main piping with valves and appurtenances, and involved open cut and directional drill installation as well as installation in an existing jack and bore casing under a railroad right-of-way. Construction of the force main project also included removal of the existing 4-inch force main and appurtenances.
MWI provided construction phase services including, attending pre-construction and progress meetings; providing contract administration and support; reviewing contractor submittals; approving pay requests; reviewing change orders; providing construction inspection; asset management compliance support; and preparing record drawings and final certifications.

Control Panel
Conduit installed at power meter

Control Panel
Surge protection installation

New Construction
Site rehab and SCADA
- Thirty-six (36) triplex pump stations.
- Ten large (10) pump stations with electrical buildings and existing PLCs/VFDs.
- Thirty (30) single phase pump stations.
- Seventy-five (75) 230/240 volt duplex pump stations.
- One hundred thirty-nine (139) 460/480 volt duplex pump stations.
Metzger & Willard, Inc. (MWI) was contracted by HCPUD through a contract with Arcadis to provide construction management services for the pump station improvements including site inspection. MWI provided one full time construction observer to check the quality of work, coordinate with the Contractor and other inspectors, prepare daily written reports, document construction progress with photos, and submit weekly reports. The MWI inspector also attended construction progress meetings, scheduled system testing, prepared punch lists, and observed and coordinated start-up testing.

South Cross Bayou
Installing 48-inch Megalug gland

South Cross Bayou
Trenching conduit at south panel

South Cross Bayou
Reclaimed water meter assembly
The goal of the project was to supply reclaimed process water to the SCBWRF but, when necessary, stop flow from leaving the plant to allow buildup of reclaimed water inventory in the on-site storage tanks. The project included the design and construction of new piping fitted with a 20-inch valve, and the replacement of the existing 36-inch butterfly valve. The new valves were designed to be automatically operated. In addition, the project involved providing automatic operation for an existing 48-inch butterfly valve. With these modifications, Pinellas County Utilities is able to automatically control flow out of the plant.
Engineering services provided by MWI included preliminary and final design, preparation of complete construction contract documents (technical specifications, drawings, bid forms and instructions, and cost estimates), bidding assistance, construction phase services, and construction observation. The total cost of the project construction was approximately $300,000.